    Electricity supply from the public grid and heat supply via district heating

    Ford-Werke, Saarlouis, Germany

    Goal

    Development of an optimized supply concept

    Partnership

    Construction of a self-generation plant and integration into the Saar district heating network

    • CHP plant with 22 MWel and 20 MWth
    • Operation of the generation plants by Iqony

    Results

    • Investment: € 23 million
    • CO2 savings: 28,000 t/a

    Impact

    Improving the environmental balance, reducing costs, strengthening the plant location

    Project facts

    Generation  
    Electricity 149,000 MWh/a
    Heat 138,000 MWh/a