    Power supply from the public grid and process steam via boiler system

    Michelin tire plants, Bad Kreuznach, Germany

    Goal

    Energy-efficient supply of steam and electricity to the tire plants

    Solution

    Operational management by Iqony, renewal of energy generation

    • Gas turbine with 10 MWel and waste heat boiler
    • Takeover of the operating team

    Results

    • Investment: € 10 million
    • Savings: 1 million €/a
    • CO2 savings: 7.000 t/a

    Impact

    Energy saving, cost reduction, ​Integration of the old system

    Project facts

    Generation  
    Electricity 72,000 MWh/a
    Steam 167,000 MWh/a