• EN
  • References

    Construction of solar park

    Tabernas II, Spain

    As the third out of four solar farms of the Tinosa Pipeline, the solar farms Tabernas II went on line in 2022. With a capacity of 50 MWp, the plant in the Spanish Tabernas desert ensures an annual electricity generation of 100,000 MWh, which is fed into the local grid via the substation “La Serrata” constructed by SENS.

    The two solar farms La Cabrita (50 MWp) and EGA (30 MWp) were completed earlier. Thus 130 MWp out of the projected 180 MWp pipeline have been connected to the grid.

    Project facts

    Location Tabernas Desert
    Country Spain
    Overall capacity 50 MWp
    Year 2022