References
Project development support and services in the waste-to-energy plant
Waste-to-Energy power plant Kochi, India – Owner's Engineer
Project Development Assistance and Pre-Award Services
For the new waste-to-energy power plant in Kochi, Iqony Solutions (IQS) has performed as an Owner’s Engineer for the project development and pre-award services:
- Review of existing project documents (e.g., feasibility report, detailed project report and site studies report)
- Review of tender bid documents (e.g., scope of supply, specification)
- Support for financial evaluation of the bid and negotiation with bidders and the local coordination
Project facts
| Installed capacity | 10 MWel |
| Fuel | Municipal solid waste, RDF |
| Technology | Waste heat recovery boiler, gasifier |
| Customer | GJ Eco Power Pvt. Ltd. |
| IQS performance period | ongoing |