BP STEAM at the refinery site Gelsenkirchen-Scholven, Germany – General contractor and maintenance
Iqony was hired by ROG as EPC for the planning, construction, commissioning and subsequent maintenance of 4 new high-pressure steam boilers with a total maximum rated thermal output of 436 MWth.
After completion of the high-pressure steam boilers, Iqony Solutions is responsible as a subcontractor for the maintenance measures for all four boilers, including all ancillary systems for a period of 5 years from the commissioning of the last boiler.
IQS provides the following services:
- Scheduled and unscheduled maintenance
- Delivery of spare and wear parts
- Consumables
- Warehouse responsibility
- Evaluation of operating data for preventive maintenance
Project facts
Installed capacity | 2 x 140 t/h (2 x 122 MWth) 2 x 120 t/h (2 x 96 MWth / 15 MWel) |
Technology | Natural circulation boiler |
Fuel | Natural gas / coke gas / refinary gas |
Customer | Iqony GmbH / Ruhr Oel GmbH |
IQS performance period | 5 years |