    Preliminary planning

    Utility supply for GREEN industrial park, Kassel-Calden, Germany - Preliminary planning

    Iqony Solutions has provided the preliminary design for the utility supply to an industrial park.

    Project details:

    • 10 local heating networks, supply temperature 70°C
    • 5 local heating networks, supply temperature 50°C
    • 5 cooling networks, supply temperature 5°C
    • 10 brine/water heat pumps, 600kWth each with geothermal probes or
    • 10 air/water heat pumps, 600KWth each
    • Borehole heat exchanger array with 1,000 geothermal heat exchangers and brine network
    • CAPEX > 10,000,000 euros
    • New build, greenfield site

    Project facts

    System capacity 6,000 MWth
    Client Iqony Solutions with EDF Deutschland GmbH
    Voltage level Medium voltage 20kV
    HOAI phases Basic evaluation, preliminary design
    IQS performance period 01/2023 – 04/2023